When you dig a basement next to an existing building, you remove the soil that was helping to hold up your neighbour's foundation. Shoring is the structure that takes over that job, during excavation and sometimes for the life of the building.

What can go wrong

An unsupported or poorly supported excavation can cause:

  • Settlement of the ground and buildings behind the excavation
  • Sideways movement of the soil towards the hole, cracking walls and floors next door
  • Loss of bearing capacity under nearby foundations
  • Water and soil flowing in through gaps, leaving voids behind the wall
  • Vibration damage from driving piles or heavy equipment

A stable excavation has three parts: a wall, a system that holds the wall in place, and monitoring that shows whether it is working.

Choosing the wall

Wall typeHow it worksGood forWatch out for
Soldier pile and laggingSteel or concrete piles at intervals, with timber, steel or concrete panels placed between them as you digFast, economical, dry groundNot watertight; soil can escape between boards
Sheet pilesInterlocking steel sheets driven or vibrated into the groundSoft ground, waterNoise and vibration next to old buildings
Contiguous bored pilesConcrete piles drilled side by side with small gapsStiff soil above the water tableGaps let water and fine soil through
Secant pilesOverlapping concrete piles that form a continuous wallWet ground, sensitive neighboursNeeds accurate drilling to keep the overlap
Diaphragm wallReinforced concrete panels cast in deep trenchesDeep basements; can become the permanent basement wallSpecialist equipment, higher cost
Soil nailingSteel bars drilled into the soil face, covered with sprayed concrete, built top-downFirm ground with space behind the faceNails extend under the neighbour's land

Holding the wall in place

A shallow wall can stand as a cantilever, fixed only by the ground below the dig. Deeper walls need support:

  • Struts and rakers: steel props across the excavation or sloping down to the base. They stay inside your site but get in the way of excavators.
  • Ground anchors (tiebacks): tensioned steel tendons drilled through the wall into the ground behind it. They keep the hole clear, but they extend under neighbouring land, so you need the owner's agreement.
  • Top-down construction: the basement floor slabs are cast as you dig down and act as permanent props.

Dealing with groundwater

If the dig goes below the water table, water has to be controlled. Pumping it out (dewatering) lowers the water table around the site, which can make neighbouring ground settle. A watertight wall, such as secant piles or a diaphragm wall, reduces how much pumping is needed.

Monitoring: proof that the neighbours are safe

  1. Condition survey before work: photographs and a written record of existing cracks in neighbouring buildings, shared with their owners. This protects everyone if a dispute arises.
  2. Settlement markers on neighbouring buildings and the street, surveyed regularly.
  3. Inclinometers in or behind the wall, measuring how much it bends as the dig goes deeper.
  4. Crack gauges and vibration monitors where buildings are old or sensitive.
  5. Trigger levels: movement limits agreed in advance, each with an action, from more frequent readings to stopping work and adding support.

The usual sequence

  1. Soil investigation, including the groundwater level
  2. Shoring design by a geotechnical or structural engineer
  3. Condition survey of neighbouring buildings
  4. Install the wall
  5. Excavate in stages, installing each level of support before digging further
  6. Build the basement structure
  7. Remove temporary supports in the order the design specifies

In Ethiopia

Under Building Proclamation No. 1356/2024, protective fences or shelters must go up before construction starts. Contractors on Category B and C buildings must provide liability insurance or a guarantee against damage from quality failures. Buildings with five or more basement levels fall into Category D, which brings the strictest oversight. Ask for the shoring design, calculations and monitoring plan to be part of the structural package, not an afterthought on site.

Frequently asked questions

How deep can you dig before shoring is needed?

It depends on the soil, groundwater and how close neighbouring foundations are. A geotechnical or structural engineer should decide, and any dig beside an existing building needs a design check.

Can the shoring wall become the permanent basement wall?

Yes. Diaphragm walls and secant pile walls are often designed to become the permanent basement wall, which saves space and time.

Why survey the neighbouring buildings before digging?

A recorded condition survey shows which cracks existed before work started. It protects both the neighbour and the owner if damage is claimed later.

Do ground anchors need the neighbour's permission?

Anchors extend under neighbouring land, so you need the owner's agreement. If it isn't given, internal struts or top-down construction are the alternatives.